Curtis Park Water Meter project schedule update 2/5/13

This week, the contractor will be performing the following:

  1. Performing a hydrostatic test on the west side of Curtis Park.  Once the hydrostatic test passes then they can pave the west side.
  2. Installing water services on Curtis Way, east side of Curtis Park
  3. Installing fire hydrants along Franklin Blvd.